1)When i am calculating my plan cost for an activity whose duration is 10days , working is 8h/day and rate is 50/hr , my plan cost is coming rs. 8000 instead of 4000. can anyone help?
After confirming an activity 100% , actual cost is not coming. Is there any customisation in confirmation or at any other place?