Hi,
I have a scheduling agreement for 1000 target qty for a component.
When i run MRP for that component where there is a requriement for 1200, it should give me an error message/information. Through MRP run i am creating schedules instead of pruch reqs, after prior master data setup in ME01.
How to configure to get an error message/information after running MRP in this case.
Please be informed that i am getting an error message/information while manually trying to add schedules to the SA using ME38.
Thanks,
Arun.