Mar 03, 2009 at 07:22 AM

Scheduling Prod.order

33 Views

Hi Experts,

Can anybody please tell me.

SMK - 1 1 1

In house prod. time - 2 days ( MRP 2 views )

There is no maintain any set,teardown,processing time in Routing.

I created two prod.order. for quntity 1 & 200.Where I got following dates.

Basic finish date - 10.03.2009

Basic start date - 06.03.2009

Why dates are common for 1 & 200 quantity. It should have take more days for 200 quantity.