Hi Experts,
I am trying to configure the PP/DS on S/4HANA & also doing the scheduling.
I am not getting teh activities while transferring the PDS which is leading to no loading on resource.
I created, Bom, Routing, Resource, PDS successfully & plaiing is giving me planned order as well with source of supply as the same PDS I generated but in planning board, I don't see the order.
Check out all the relevant screen shots & let me know if you can pin point the problem.