Hi
suppose i have a activity duration from 1st february 2009 to 28th february 2009
on 15th february i confirm 0nly 10% of the work as completed in the activity confirmation screen in the degree of processing field and also enter the start date as 1st february 2009 and the finish date as 15th february 2009.
when we look at the planning board in CJ20n transaction subsequently (gantt chart) the activity bar shows a colouring from 1st february to 15th february instead of showing only 10% of the activity bar coloured for completion of the work
where is it possible to see the percentage completion of an activity graphically as 10% this data is available in table format in CN48N transactio