Skip to Content
avatar image
Former Member

Error cProject 4.0 after update

Hi experts,

We have updated cProject 4.0 from SP8 to SP13 (CPRXRPM for ABAP and BPPPMDC for Java).

Now we have this error when we try to launch cProject :

The following error text was processed in the system EC6 : Syntax error in program /1BCWDY/YXA35AAEJAF59288U1RW==CP . 
The error occurred on the application server SERVER_EC6_00 and in the work process 0 . 
The termination type was: RABAX_STATE 
The ABAP call stack was: 
Method: CONSTRUCTOR of program CL_WDR_CLIENT_COMPONENT=======CP
Method: IF_WDR_COMPONENT_FACTORY~CREATE_COMPONENT of program CL_WDR_CLIENT_COMPONENT=======CP
Method: IF_WD_COMPONENT_USAGE~CREATE_COMPONENT of program CL_WDR_COMPONENT_USAGE========CP
Method: CREATE_UNINITIALIZED_VIEW of program CL_WDR_VIEW_MANAGER===========CP
Method: GET_VIEW of program CL_WDR_VIEW_MANAGER===========CP
Method: BIND of program CL_WDR_VIEW_MANAGER===========CP
Method: IF_WDR_VIEW_MANAGER~MAKE_VISIBLE of program CL_WDR_VIEW_MANAGER===========CP
Method: PERFORM_NAVIGATION of program CL_WDR_CLIENT_APPLICATION=====CP
Method: NAVIGATE of program CL_WDR_CLIENT_APPLICATION=====CP
Method: DO_NAVIGATION of program CL_WDR_WINDOW_PHASE_MODEL=====CP

AS Java is SP9, do we have to update it ? if yes, which SP ?

Thanks in advance,

Mik.

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

8 Answers

  • Best Answer
    Mar 04, 2009 at 05:30 PM

    Hi,

    SAP Note 1171775 should fix the issue.

    Kind regards,

    Florian

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 03, 2009 at 01:05 PM

    Hi,

    (1) yes

    (2) as mentioned above: always use the same SP for NW ABAP and Java/EP stack. Java / EP stack is only needed if you use the BP for PPMDC.

    Kind regards,

    Florian

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 03, 2009 at 11:20 AM

    Hi,

    before implementing a new cProjects 4.0 Support Package, please always have a look at the following SAP Notes:

    - SAP Note 905959 Dependencies between cProjects 4.0 SPs and NW 7.0 SPs

    - SAP Note 862198 Notes to be implemented after a particular cProjects 4.0 SP

    Please also make sure that you have always the same NW SP for ABAP and Java stack.

    Kind regards,

    Florian

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 03, 2009 at 12:46 PM

    Thanks Florian!

    I have read the note 905959. I have two questions:

    1. the note doesn't contain information about cProjects 4.0 SP13.

    Do you think that requirements for SP12 are valid for SP13

    --> point 13 of the note : cProjects 4.0 SP 12 requires NetWeaver 2004s SP12 or higher ?

    2. NetWeaver 2004s SP12 means AS Java and AS ABAP SP12 (=> kernel update via JSPM / SPAM... )

    or just AS ABAP <=> SAPKB70012 & SAPKA70012 in SPAM ?

    Mik.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 04, 2009 at 09:27 AM

    Hi,

    Now, I have ABAP SP12 + JAVA SP12.

    SAP_BASIS 700/0012

    SAP_ABA 700/0012

    PI_BASIS 2005_1_700/0012

    SAP_BW 700/0012

    When I launch cProject using http://server.domain.ext:8000/sap/bc/webdynpro/sap/cprojects for instance,

    I still have the error :

    The following error text was processed in the system EC6 : Syntax error in program /1BCWDY/YXA35AAEJAF59288U1RW==CP . 
    The error occurred on the application server SERVER_EC6_00 and in the work process 0 . 
    The termination type was: RABAX_STATE 
    The ABAP call stack was: 
    Method: CONSTRUCTOR of program CL_WDR_CLIENT_COMPONENT=======CP
    Method: IF_WDR_COMPONENT_FACTORY~CREATE_COMPONENT of program CL_WDR_CLIENT_COMPONENT=======CP
    Method: IF_WD_COMPONENT_USAGE~CREATE_COMPONENT of program CL_WDR_COMPONENT_USAGE========CP
    Method: CREATE_UNINITIALIZED_VIEW of program CL_WDR_VIEW_MANAGER===========CP
    Method: GET_VIEW of program CL_WDR_VIEW_MANAGER===========CP
    Method: BIND of program CL_WDR_VIEW_MANAGER===========CP
    Method: IF_WDR_VIEW_MANAGER~MAKE_VISIBLE of program CL_WDR_VIEW_MANAGER===========CP
    Method: PERFORM_NAVIGATION of program CL_WDR_CLIENT_APPLICATION=====CP
    Method: NAVIGATE of program CL_WDR_CLIENT_APPLICATION=====CP
    Method: DO_NAVIGATION of program CL_WDR_WINDOW_PHASE_MODEL=====CP

    in ST22 :

    Short text

    Syntax error in program "/1BCWDY/YXA35AAEJAF59288U1RW==CP ".

    What happened?

    Error in the ABAP Application Program

    The current ABAP program "CL_WDR_CLIENT_COMPONENT=======CP" had to be

    terminated because it has

    come across a statement that unfortunately cannot be executed.

    The following syntax error occurred in program

    "/1BCWDY/YXA35AAEJAF59288U1RW==CP " in include "/1BCWDY/B_EPFSCZNUPMJYS6LLZULT

    " in

    line 4327:

    "The obligatory parameter "IV_INITIAL_CALL" had no value assigned to it"

    "."

    " "

    " "

    The include has been created and last changed by:

    Created by: "USER"

    Last changed by: "USER"

    Web Dynpro Component DPR_ENTRY

    Web Dynpro Controller VI_ENTRY_CREATE

    What can I do ?

    Mik.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 04, 2009 at 06:34 PM

    Thank's a lot Florian.

    With the implementation of this SAP Note, cProject is working.

    Best regards,

    Mik.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 04, 2009 at 08:37 PM

    ShortDump on Gantt View : DPR_GANTT component

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Mar 04, 2009 at 08:41 PM

    Hi,

    I open this thread again because the gantt view in cProject doesn't work.

    The error is :

    The following error text was processed in the system EC6 : Syntax error in program /1BCWDY/H463YNKSJN9B1KVNOWY0==CP . 
    The error occurred on the application server SERVER_EC6_00 and in the work process 0 . 
    The termination type was: RABAX_STATE 
    The ABAP call stack was: 
    Method: CONSTRUCTOR of program CL_WDR_CLIENT_COMPONENT=======CP
    Method: IF_WDR_COMPONENT_FACTORY~CREATE_COMPONENT of program CL_WDR_CLIENT_COMPONENT=======CP
    Method: IF_WD_COMPONENT_USAGE~CREATE_COMPONENT of program CL_WDR_COMPONENT_USAGE========CP
    Method: CREATE_UNINITIALIZED_VIEW of program CL_WDR_VIEW_MANAGER===========CP
    Method: GET_VIEW of program CL_WDR_VIEW_MANAGER===========CP
    Method: BIND of program CL_WDR_VIEW_MANAGER===========CP
    Method: IF_WDR_VIEW_MANAGER~MAKE_VISIBLE of program CL_WDR_VIEW_MANAGER===========CP
    Method: PERFORM_NAVIGATION of program CL_WDR_CLIENT_APPLICATION=====CP
    Method: NAVIGATE of program CL_WDR_CLIENT_APPLICATION=====CP

    The stack:

    Short text

    Syntax error in program "/1BCWDY/H463YNKSJN9B1KVNOWY0==CP ".

    What happened?

    Error in the ABAP Application Program

    The current ABAP program "CL_WDR_CLIENT_COMPONENT=======CP" had to be

    terminated because it has

    come across a statement that unfortunately cannot be executed.

    The following syntax error occurred in program

    "/1BCWDY/H463YNKSJN9B1KVNOWY0==CP " in include "/1BCWDY/B_YB11CB9VIX5R8H0SWD1N

    " in

    line 550:

    "The "IS SUPPLIED" query makes sense only for optional parameters."

    " "

    " "

    " "

    The include has been created and last changed by:

    Created by: "USER"

    Last changed by: "USER"

    Web Dynpro Component DPR_GANTT

    Web Dynpro Controller WI_DPR_GANTT

    I have found some notes about DPR_GANTT component problem but no sap note for this specific problem.

    Any suggestion ?

    Best regards,

    Mik.

    Edited by: Mik Deb on Mar 4, 2009 9:53 PM

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member

      Problem solved.

      SE80

      Web Dynpro Component DPR_GANTT

      Window WI_DPR_GANTT

      Method HANDLEIP_GANTT

      Check Optional for COLLAPASE parameter

      Mik.