Dear all experts,
could you help me on this question?
it almost drives me crazy.
after i create a project, i do the project scheduling(forward, network determine dates, bottom-up).
and then i get the earliest (latest)start and finish dates of each activity.
the dates are very important, because they need to be compared with the actual confirmed dates as the project proceeds. therefore, i want to hold the earliest (latest) start and finish dates of each activity unchanged unless i change the duration and reschedule.
but the fact is after i do one activity partial confimation, i find the scheduled dates of all activities are changed.
The earliest start date of the partial confirmed activity is calculated from the confirmed actual start date.
how can i avoid this?
do i need to config?
could you give me some hints?
i need to do the partial confirmation, and i also have to keep the scheduled dates of activities as well
how can i achieve it?
thanks a lot
Judy