Dear All,
My Project stock is Non-Valuated.
I am attaching material to an internal activity with reservation (i.e. reservation for WBS).
I am running Project level MRP (MD51) and generating PR.
Currently, when we run MRP in MD51, it consider only Project Stock i.e. even the material is available in unrestricted warehouse, it will not consider that stock and will generate PR for attached quantity. My client, want that when we run MRP, system should consider that Plant level Warehouse stock and should give requirement for shortage qty.
Let me know how we can do this??
Thanks and Regards,
Atul R. Rajmane