dear ps experts,
kindly let me know what is the right process in dealing with Project stock items issue for customer project.
1. Is it thru MIGO-Goods Issues to Project against Reservation number
2. Delivery thru Sales order - Delivery thru VL01N - PGI from project stock
We are successful thru sales order - delivery thru vl01n - pgi and unable to settle the Reservation number in Project, which is still showing as "Reserved" through MMBE against the same material after delivery thru
Pl help in clarifying us the right process.
Regards