Dear All

I am facing a typical problem as given below

In production order there are 2 PP operations and 1 QM operation Like below

10 operation PP Operation with Mile stone control Key

20 operation QM Operation with Mile stone control Key

30 operation PP Operation with Mile stone control Key

My Problem is that when users are confirming 30th operation 20 is also automatically confirmed (Which should not be as it itself is milestone)

How to rectify that problem. My requirment is that 20th operation should not confirm while confirming 30th operation and i cannot remove milestone from 30the operation also.

If 20th operation is not at all confirmed then 30 cannot be confirmed but if 20 is PCNF then 30 can be confirmed and with that rest of the quantity of 20 is also confirmed

Pl.Help

Edited by: vishnu agarwal on Mar 2, 2009 11:26 AM