on 03-02-2009 9:35 AM
Dear Friends ,
Scenario is as follows
Material is batch managed
Inspection type 03 - In process inspection
Process order is released inspeciton lot created for in process inspection
but in production the batch number is generated during GR and have multiple batches
but issue is when i do UD for inspection lot which is created during order release system is asking for batch number
but i want to usuage decsion with out batch
can any one suggest how to solve the problem
Thanks & Regards
Raj
closed
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Rajkumar,
If you do not want to create the partial lot and assignment of batch, than check your Recipe or rauting data , In the QM Headed data for recipe For " Partial Lot assignment " you shold put option 4 - Partial lot and batch of last operation.Than system will n ot ask to put batch no on UD.
Pl check and revert back if any dout.
Regards,
Neeraj
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.