Dear all,
i trying to update the standard cost of a material and those components that are in its multi-level BOM.
Scenario:
Material Level Std Cost
A 1 $0
|
B 2 $1
|
C 3 $0
Material A has 3 levels in its multilevel BOM. I trying to update the std cost of material A and C without updating cost of B and std cost of B was previoulsy updated by CK24.
I tried to use transfer Control in CK40N but transfer Control once recongise that its BOM has a std cost won't procced on to the next . Is it possible whereby i can updates cost of those selected materials and their multilevel BOM that do not have a cost estimate?
Regards
YM