Hi Gurus,
We are implementing the concept of Planned Independent Requirements(PIRs) in SAP AFS.
Below is the process am following :
1. Create PIRs.
2. Create a Purchase Requisitions.
3. Create Sales Order.
I am using the concept of forward consumptiona and planning strategy 40 for the PIRs consumption.
Also I understand that the Sales order will consume the PIRs.But when I go the stock Requirements
list I dont see any changes happening.I mean I dont see any linkage between the Sales Order or the PIRs.
Please help on the above concept,Am trying to understand how does the concept of PIRs work and how can I simulate and see the results in SAP.What will happen to the PIRs and SO and how can I see the linkage that a Particular Sales Order has consumed the PIR.
Any help on this would be appreciable.
Thanks,
Jinen