Dear All,
We are created strategy based maintenace plan like this
1)Equipment valid from 01.01.2009
2)Equipment task list 01.01.2009
3) Scheduling period :360 days
4) Start of cycle:04.12.2008
5)Scheduling indicator :Factory calendar
6) Frequency:30,90 days
We are schedule maintenance plan then we will get 14 call objects.But problem is scheduling period 360 days then we are expecting 12 call objects.
Pls.help me logic.