Dear friends,

We are maintaining the Material cost, Maintenance cost everything in INR. So, when the Internal Material cost for any PM order is taken the INR is displayed.

But now if I need the report of all the Internal Costs or any costs in general for PM Orders for a specific period then I find the difference in the cost displayed in Order to that displayed in MCI8 report.

As I understand, MCI8 report is default maintained in EUR but I am actually using the Exchange Rate M for the conversion into INR.

Though, I expect some variation or difference in the cost due to different currency maintenance, but actually the variation am observing is more than 6 -10% .

Please suggest me on how to proceed further.

Thanks a lot!