Production order without material status update - header

325 Views

Hello

We are issuing production order without material ( CO07 ). While confirming the order , the components are issued to the cost center and document are updated, If we are issuing 50 lb for the header material the material status is not changing , still showing 0 delivered . How to update the status of the operation with progress confirmation has been confirmed. Currently we are getting GMPS Goods movement posted , But we need to get DLV status with 50 lb in the delivered feild .Any help will be highly appreciated