Feb 27, 2009 at 03:01 PM

Avilability control - budget

25 Views

Hi,

i have made following settings

Budget profile

availibiity control

type-1

overall- selected

annual- selected

tollernace limit

90 % - 1 ( warning)

100% - 2 (Warning with mail)

now in projects i am havin onlyone 1st level WBSE

& other WBSE at different levels.

EX- ABCD-1 ( PD)

ABCD-1 (1st level WSBE) 500 (Budget)

ABCD-1-10 (2nd level WBSE) 300 (budget)

ABCD-1-10-Z (3rd level WBSE) 200 (Budget)

ABCD-1-10-X (3rd level WBSE) 0 (Budget)

now as per tollerance limit system should not stop any transaction because of budget.

I created PO with ABCD-1-10-X wbse amount 500 Rs.

system thows error that budget exceeded for WBSE- ABCD-1-10.

system should not through error when we set tollerance limit for warning with mail.

regards,

Venkatesh