Hi All,
I have a ROH which has direcet procuremnt (53) and planned delivery time of 2 days in matl master.
BOM of FERT has only this ROH.
When I create production order with "Current Date" scheduling, the purchase requistion is created automatically for the ROH. A scheduling log is created for a warning message "Can delivery date for material ROH be kept? Realistic date: 05.03.2009. System sets delivery date of ROH to past date.
My requirement is since this is direct procurement process, the system should propose the delivery date for ROH as 2 days from current date (Plnnd Delivery time) accordingly production order "Schduled start" date should be postponed for two days eventhough it is current date scheduling.
Looking forward your valuable answers.
Thanks
Guru