Hello,
When planning independent requirements are entered for the date which is not the first day of the month and also a non-bussiness day, date is displaced with previous bussiness day, there is no problem with this process.
When planning independent requirements are entered for the non-bussiness day which is the first day of the month(01.09.2018), date is displaced with the last day of the previous month(31.08.2018) at MD61 transaction code. We need to displace that date for the next bussiness day of the current month(03.09.2018), is there any way to do this? (with planning period D- Day)
Thanks
[MRP-3 Strategy Group- 40 (Planning with final assembly)]
Hello
It is a standard system behavior to move requirements in a non-working day to the previous working day. This is the default system behavior, in order to avoid the production to be executed too late and a possible shortage.
Regards,
Caetano
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hello Caetano,
I know the standart system rules but I'm wondering that there will be another way? I need to determine my requirements monthly. If the first day of month is holiday, requirement of that day should not be transferred to other month.Requirements are created by BAPI_REQUIREMENTS_CREATE function. If i can't find solution and the first day of the month is a non-bussiness day, i will determine the next bussiness day manually and use that date in function.
Best Regards,