Dear all,
i meet a problem. could you help me on it?
i created the project with many activities and used project scheduling to determine the start and finish dates of each activity.
these start and finish dates are very important when they are used to compare the actual dates.
the project lasts for almost a year.
several months later, i suddenly found the scheduled start and finish dates of activities changed.
the change is irregular.
but i compare them with the orignial data in EXCEL, they are totally different.
i used CN60 to check the change documents, and found the basic finish date of network changes from time to time. it seems that when i opened the project and save, the project is re-scheduled. but i am not sure if the activity change is caused by the network date change.
there are materials assigned to the activities. and the PR
and production order will be created accordingly. will the date of the orders affect the dates of the activities?
can you explain the reason for me?
I just want to have a project in which the dates are unchangeable except by the owner.
is there anything important in the configuration to achieve it?
thanks a lot .
Judy