I want to know why the system does not issue error when there is value differnce between the Target value and all Line item Values for service value contract......

Like service contract Targat value is 10000 USD

If all line item value of services is more than 10000 USD the system is accepting But Normally the system should not accept....Is there any message for the system to check between the target value and all line item value...

Let me know...

Thanks,

Bindu

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Feb 26, 2009 at 04:26 PM

    The target value validation is done at the time of posting of subsequent documents referring the contract. The purpose of the target value at header level is for that purpose only

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.