Feb 26, 2009 at 11:08 AM

Simple discontinuation Cycle

43 Views

Hi

Simple Discontinuation cycle.

Material : XXXX, Component : YYYY & ZZZZ(Component : YYYY will be discontinued and replaced by ZZZZ)

I have given the effective out date as today 26.02.2009. I maintained the BOM for XXXX with components YYYY and ZZZZ and maintained settings at item level for replacement.

I created a PIR for XXXX u2013 125nos and have stock for Component YYYY u2013 100nos. Now I run MRP for Material : XXXX and I have got a Planned order for ZZZZ for 125nos and Component YYYY I have got a reservation u2013 100nos and the remaining 25nos proposals are not created and also its not transferred to ZZZZ which will replace YYYY..

Can you get back to me on the above?

Jade