on 06-30-2018 12:05 PM
Hello Sir,
I had created general task list for A equipment in 1100 plant and same equipment was present in 1200 plant . I want to create Preventive maintenance plan for equipment in 1200 for same task list. how can i assign same task list.?
In general task i had enter work center for 1100 plant , so how can i proceed?
Thank You.
Hi Gaurav,
This depends on your planning plant. If the planning plant is same, then same task list can be used. else you need to create a separate Task list for each planning plant.
Planning Plant field in the task list header will be greyed out, after it has been used in maintenance plan.
Regards
Terence
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank You Sir.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thank You Sir,
If there are 3 work centre in same plant , can we assign same task list for maintenance plan?
Any Solution for -Single task list for two equipment which are installed in two different plant ?
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Different work centres can be assigned to Task List Operation.
If you go for General Task List, it can be used for multiple Equipments to one specific planning plant.
Any Solution for -Single task list for two equipment which are installed in two different plant ?
If two different plants, its better to have separate Task List.
Regards
Terence
User | Count |
---|---|
85 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.