No CTS projects found for "project TEST"

155 Views

Hi Experts, I´m configuring the Change Request Managment for Solman 7.0 SP16, but when I execute the check report (/tmwflow/charmchk) appear the following issues:

Check consistency of "project TEST"

--> No CTS projects found for "project TEST"

When I execute de logistic report (/tmwflow/proj) I view that:

- the "Project Structure" status is green and I can view that the Cycle is active and CTS Project is assigned.

- The "CTS Status Switches" status is green and I can view the status of my project TEST.

When I create the IMG Project, the logistic report was in red, but applied the notes:

1158885 Maintenance cycle/project cycle cannot be completed

1163568 No completion of task list; CTS project active

And the status was changed to green, but the charm check said No CTS projects found for "project TEST"

Any idea to solve that?

Regards,

Sergio.