Dear PP Experts,
I have a BOM of semifinish Material "A" which includes
semifinish material "B" with quantity 1
raw material "C" with quantity 1.
semifinish material "B" with quantity 1
As "B" is having 2 alternative bom.
In alternative 1:- materials are- "D" qty 1
"E" qty 2
In alternative 2:- materials are- "D" qty 1
"F" qty 2
While MRP run on "A" system capturing only alternative 1 of "B" in MRP. My client wants system should capture both the alternatives.
Pl. help me regarding this issue.
Thanks,
Regards,
Sachin Patil