ALTERNATIVE BOM SELECTION IN MRP RUN

Dear PP Experts,

I have a BOM of semifinish Material "A" which includes

semifinish material "B" with quantity 1

raw material "C" with quantity 1.

semifinish material "B" with quantity 1

As "B" is having 2 alternative bom.

In alternative 1:- materials are- "D" qty 1

"E" qty 2

In alternative 2:- materials are- "D" qty 1

"F" qty 2

While MRP run on "A" system capturing only alternative 1 of "B" in MRP. My client wants system should capture both the alternatives.

Pl. help me regarding this issue.

Thanks,

Regards,

Sachin Patil

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Feb 25, 2009 at 01:44 PM

    Can you let us know why you want both of them to be selected?

    If it is the need, then why create an alternative?

    Regards,

    Vivek

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      You can make alternate BOM selection by following procedure :

      For BOM Alternative Selection you need to maintain any of the following settings in Material Master --->

      MRP-4 View->BOM Explosion / Dependent Requirements->Selection Method :

      Method for Selecting Alternative Bills of Material

      Indicator determining the selection of the alternative BOM when requirements are exploded in material requirements planning.

      Use

      With Selection by order quantity, the system chooses the alternative BOM into whose lot size range the order quantity falls. The lot size range and area of validity of the BOM apply.

      With Selection by explosion date, the system chooses the alternative BOM into whose area of validity the date falls according to the setting BOM via dates.

      With Selection by production version, the system chooses the alternative BOM defined in the valid production version. The lot size range and area of validity of the production version apply.

      With Selection only by production version, the system chooses the alternative BOM defined in the valid production version. The lot size range and area of validity of the production version apply.

      If no production version is found, no production orders or process orders can be created.

      Hope this helps.

      Revert if any doubt.

      Regards,

      Tejas

  • author's profile photo Former Member
    Former Member
    Posted on Feb 25, 2009 at 01:47 PM

    Hi,

    As Vivek told, If you need both of them together then there is no need of alternate BOM.You need to maintain components E & F in single BOM only of B.

    Further if it is required to have both BOM components together in certain conditions only then you can go for Variant BOM by maintaining OD for components and hence you can use single BOM only.

    However pls clarify your requirement in more details to fulfill your requirement.

    Regards,

    Tejas

    Edited by: Tejas Pujara on Feb 25, 2009 2:48 PM

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.