Delay Report

Dear PS Gurus,

Is there any report which informs progressive delays of the project ?

I am precisely looking for a report which calculates delay,In CNS41 report system is calculating

project delay by cumulating delays in all WBS element. Hence delay is shown in

multiples ( some thousand days). Ideally it should calculate based on earliest

start & latest finish of WBS elements.

This is creating a totally wrong report of progress.

Expecting inputs on this.

Regards,

Abhijeet Patil

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Feb 25, 2009 at 03:04 PM

    Hi,

    Try to test CN41N. Change layout & add delay column. Additionally you may use exceptions to highlight chosen lines.

    Kind regards, Aleksandra

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.