Dear PS Gurus,
Is there any report which informs progressive delays of the project ?
I am precisely looking for a report which calculates delay,In CNS41 report system is calculating
project delay by cumulating delays in all WBS element. Hence delay is shown in
multiples ( some thousand days). Ideally it should calculate based on earliest
start & latest finish of WBS elements.
This is creating a totally wrong report of progress.
Expecting inputs on this.
Regards,
Abhijeet Patil