External operation without material supply

Hi, i want to send only the parent material (header material) for some operation at subcontractor for operation 20. pls advise how to maintain the bom and send to vender and further steps? thank u in advance.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Feb 25, 2009 at 12:05 PM

    Hi,

    Pl. find below steps for external processing. I got this from one of my friend.

    1. For a production material (1001), one raw material (2001) is assigned.

    2. Production process of 1001 is having four operations 10, 20, 30 and 40.

    3. In this 10, 30, and 40 are internal operations and 20 is external operation (sub-contracting).

    4. To address this, we created a dummy material (non-valuated) and named as 1001-20 (Finished product number + Operation to be performed).

    5. This 1001-20 should form part of the component in BOM of 1001. That is BOM of 1001 will have components as raw material 2001 and this dummy material 1001-20. In routing, assign this dummy material 1001-20 to operation 20.

    6. During BOM creation, you should remove costing relevancy for the item 1001-20.

    7. In routing, operation 20 is created with a work center (which is external operation work center) with exteranl operation control key.

    8. In operation details, for external processing, assign the info record of external processing.

    9. Info record of external processing has to be created for vendor with relevance to the operation to be performed externally with vendor. (We are using material group field in the external processing in routing operation).

    10. When create production order with above set up, system will create Purcha Req for external operation. This has to be converted to purchase order.

    11. Now, this dummy material should be kept as 5000 or 6000 in stock using 561. When Purchase order is raised, required quantity has to be moved to vendor using 541. When we do goods receipt the stock with vendor shall come down. With this, we can monitor the material (with dummy material number) stock with vendor (please note we can see only quantity and not value) .

    12. When we do GR for external purch order, we receive only the operation performed. (So, coversion cost to vendor shall be paid).

    13. After ensuring GR is done, order confirmatin of operation 0020 has to be done. (here we capture the quanttiy and also the valuation of material in production order).

    Madhava

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Feb 25, 2009 at 12:06 PM

    Hi,

    We need to maintained the control key with external operation in routing and then go for the operation wise confiramation.

    As soon as u create the production order an PR is created for external processing and can be seen in production order.

    U need to defined the external S Loc for vendor and has to do the 541 mot. type.

    Then do the GR againt the PO .

    hope this will answer ur query.

    Regards

    JB

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.