Hi PM experts,

We have came up with a requirement when entering time confirmations on PM orders.

PM orders contain a task list with 2 tasks.Times spent on each task is captured & the Personnal number of the task performer is entered.

Let say that three technicians have carried a maintenance task of an Equipment at the same time.

So it is required to record all three Personal Numbers for that time spent on maintenance in the Order Confirmation .

But our configuration supports to enter one Personal number per confirmation at the moment.

So how could we cater this?