Hi QM Gurus,

There is already a PO with a vendor, Who has completed supply of 30% the PO quantity.

It is required to stop the supply from that vendor. Is it possible?

Thanks in advance

Ashish

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    avatar image
    Former Member
    Feb 25, 2009 at 09:50 AM

    Hi Ashish

    In quality inforecord you can maintain the released quantity,so when this quantity exceeds

    GRN will be blocked

    Thanks

    Vinay

    Edited by: vinay joshi on Feb 25, 2009 3:20 PM

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 25, 2009 at 09:21 AM

    Yes, it is possible through blocking reason to be maintained in the quality info record.

    Further GR from a vendor can be blocked

    Hope this will solve your perpose

    Regards

    Nikhilesh Ray

    Add comment