Is it possible to do a mass update for the costing sheet field in multiple activities? We tried to use tcode CNMASS but we weren't able to find the costing sheet in the Activities tab as a valid selection criteria. Is there a way to make this field available in CNMASS? We have around 10,000 activities whose Costing Sheet needs to be changed. We want to know if the project master data update should be done somewhere else. CATT script is another option that we're looking at but it looks very complicated right now.

Thanks a lot!

Joey

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

4 Answers

  • Best Answer
    avatar image
    Former Member
    Feb 25, 2009 at 06:59 AM

    Hi,

    In my opinion, WBS costing sheet will be given preference during overhead calc over costing sheet at network activity. So try changing WBS costing sheet by mass chnage, test run overhead calc to validate.

    Regards

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 25, 2009 at 08:14 AM

    Hello Joey

    CNMASS does not have the field and there are easier ways of doing this than trying to add the field to the program

    In your case:

    If you have ABAP help

    1) Easiest way is to record the transaction in SHDB and run them in background for all the 10000 activities.

    2) Or as suggested above use that BAPI or BAPI_PROJECT_MAINTAIN to correct the activities.

    If you do not have ABAP help

    The catt scripts will be the easiest option. Half an hour tinkering with catt can be useful to you in many ways.

    Regards

    Renjith

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 25, 2009 at 08:43 AM

    have you tried LSMW?

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 26, 2009 at 12:04 AM

    Hi Everyone,

    Thanks for the responses. We decided to create a custom program instead to accommodate the requirement. Apparently, there is really no way to modify the Costing Sheet of the Network Activities using CNMASS.

    Thanks and regards,