created release startegy based on plant as critera

but in service entry sheet i no where see the plant field in ML81N then how the system is going to block the entry sheet based on plant

Accepted Solutions (1)

Accepted Solutions (1)

former_member581212
Active Contributor
0 Kudos

hi,

I think it will be determined from the linkage between PO and service location defined for that plant in the SES.

Hope it helps..

Regards

Priyanka.P

Answers (1)

Answers (1)

Former Member
0 Kudos

Hi,

You have created PO, in which you have mentioned plant.

Now you are creating Service entry sheet w.r.t. PO.

So linking of plant is coming from PO.