Dear All

When I am Running MRP with LOT SIZE as "MB" (Monthly Lot Size)

System Is raising Planned Order,

My requirement is instead of Planned Orders I need system to raise Purchase Requisition

Regards

Chaitanya

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

As answer was useful and above that the analysis is my part I am closing the issue

Former Member
0 Kudos

Hi,

Pl. use create purchase requisition indicator value as '1' or '2' while doing the planning run.

Regards,

Prithviraj

Former Member
0 Kudos

Hello ,

It is because of the procurement type "X" in MRP 2 view of material master . IF you change it to "F" , your problem will be solved