Hello,

we are using time based maintenance plans to schedule our maintenance obligations towards customers. After creating the plan and scheduling (IP10) we get the scheduled calls proposed by the system.

Now we want to use IP10 or IP19 to move those planned call dates that are in the future without releasing the predecssor calls but it gives us an error: "Maintenance plan 16.04.2009: Predecessor to still on hold".

Does anyone know if there is a way around this?

Thanks,