We currently have all materials managed at IM level and planning to implement WM.

We have three types of manufacuring process Discrete, Process, Repetitive in place. If we plan to have WM-PP interface, then

1. Is it possible to support all the three manufacuring types with WM-PP interface

2. If we can then how to differentiate the setting in wm-pp interface.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Feb 25, 2009 at 09:04 AM

    Hi ,

    You have to Maintain the standerd setting that are maintained for wharehouse 001.

    It will work for all the proces you have maintioned depend upon you WM movement type settings.

    Pls cleare the 2nd point refer the SPRO path

    Logistic execution--warehouse managment -- interface -- defie production --

    in this maintain proction supply area assighn replanishment mvt type (100) material staging indicator assighn production profile sheduling profile PP interface active