HI Gurus,
Quick question on ur.gent correction using Solution Manager CHaRM in EHP1. Is it possible to create multiple transport request(TR) for single ur.gent correction (UC). DO NOT confuse with transport task.
For example, after I created transport request and developer start working and release the task, realised to add another transport request for same UC. When I tried, it did not create any TR but checked the message found that
Schedule Manager: Monitor
Job Status: Processing completed, but with warnings
Program Name: /TMWFLOW/SCMA_TRORDER_CREATE
Action to be checked: Ur.gent Correction: Create Transport Request
There is already an open request, XXXXXXXXXX, for this project
So only way I can do that I released the TR and able to create another TR.
May be wondering why I need to create another TR, why not create TASK and work on that.
But this is the requirement at our company.
I will appreciate the effort and time to provide me the solution of this.
Thanks
Ava