Hai,

I created Master Recipe with status = 'Created' (=1) using Engineering change number ABC1 on 10th jan 2009.

Then, on 10th Jan 2009 I created a Planned order # 1 with start date 24th Feb 2009 (& planned opening date 24th Feb 2009) which automatically has recipe staus 1 (created).

On 10th Feb 2009, I released the Recipe using engineering change number XYZ1. because ABC1 was valid only for 10th Jan 2009. XYZ1 is valid only for 10th Feb 2009.

I tried to convert the Planned order # 1 to process Order on 10th Feb 2009, but received the below error message

"Master Recipe not releaseed- Message number 40102".

How do I resolve this issue?

Thank you in advance.

Sonali 😊