How to set DLV status for process orders in mass processing

How to set DLV status for process orders in mass processing

Reagrds,

Amit

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • author's profile photo Former Member
    Former Member
    Posted on Feb 24, 2009 at 04:16 PM

    Hi Amit,

    If the last operation in the SFO has PP03 control key, then mass confirm the last operation or order & DLV status will be set (use COHV)

    Alternative use MIGO & post GR for all orders, the status will be set.

    Hope the above is helpful.

    Regards,

    Vivek

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Can you let us know why you want to set DLV status w/o receiving the material into stock?

      Added

      You have marked the thread as answered, without providing any proper info or letting the forum know if the input provided was ok or not, nor awarded any points.

      I am surprised by your attitude.

      Edited by: Vivek on Feb 25, 2009 1:01 AM

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.