Delivery schedule issue in PO

Former Member
0 Kudos

Hi,

when creating PO item via PR, i find one PO item have several relative delivery schedule item, and each delivery item generate from same PR.

Example,

Item 10

Material A 37 Qty's

I am getting Delivery schedule with multiple schdule lines with splitting the total Qty's for same Purchase Req

Can you explain how this happening for One PO item.

I am getting this for Intra Company STO.

With Regards

Ram.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

ok

JL23
Active Contributor
0 Kudos

Please check the delivery that got created for your PO.

Does it have several items (maybe with different delivery dates )?

Former Member
0 Kudos

Hi,

Pl check if scheduling lines are maintained for this?

Check in Tcode ME39.

Revert back

Uts

Award if helpfull

Edited by: utsa agr on Feb 24, 2009 3:51 AM

Former Member
0 Kudos

No schedule lines maintained for this.

With Regards

Ram

former_member633418
Contributor
0 Kudos

Hi,

check whether you have maintained scheduled dates in the PR. Also check the P.O in item details delivery tab..You moght have maintained there also.

Award if helpful

former_member633418
Contributor
0 Kudos

Hi,

check whether you have maintained scheduled dates in the PR. Also check the P.O in item details delivery tab..You might have maintained there also.

Award if helpful

Former Member
0 Kudos

I am getting the schedule lines when iam creating a PO with ref to a PR.

There is no delivery created for the PO.

Nothing defined in the delivery tab.

With Regards

Ram