Feb 24, 2009 at 07:57 AM

MRP Opening period: PR instead of Planned Order

318 Views

Hi,

Would like to ask if lot size not equal to EX have a bearing in generating PRs instead of planned orders for materials which opening period falls outside our define float for opening period?

The defined opening period for us is 7 days. We are using lot size PK - period lot size accdg to planning calendar which we defined as QTR for quarterly. For this items, even if the opening period falls > 7 days from MRP run date, the system still generates PR instead of Planned order.

I tried changing the lot size into EX-lot for lot and run MD03 for 1 item, the system generated Planned order. Hope you could help enlighten me on this part.

Thanks,

MM