Hi
I am confused about the lead time to be entered for the item planning/MRP.
Do I include weekends when entering lead times in Items master data or not?
2 weeks = 10 days or 14 days?
In MRP I can select to respect Holidays. Does that also influence calculation of weekends as well or are weekends respected anyway?
Thanks
Franz