hi,
i did config settings related to Budget & availability of control
1. Maintain Budget profile --- OKOB
2. Maintain Number Ranges For Budget -- Ok11
3. Define Tolerence limits for availability control -- OKOC
4. Specify Exemt cost element from availability cintrol -- OPTK
5. Maintain Budget Manager - OK14
6. Internal Order Creation - KO01
7. Budget Change - KO22
When i want do the budget change system is giving error that Overall budget and/or annual budget cannot be processed for this how i have to proceed & what necessary settings to be done after this
Budget Allocation first how we have to do From PS/ CO direct
with regards,