Could any one tell me how to validate the Cost Center in "Purchase Requisition" with K.?

Our Validation requires/Plant. Is there any way other than "Security"?

Thanks in advance,

Vamsi

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Feb 24, 2009 at 04:33 AM

    Vamsi,

    You can only restrict the account assignment cat. K to the users by authorization profile.

    Regards,

    Manish

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Feb 24, 2009 at 04:51 PM

    Hi Vamsi,

    I think your purpose can be solved by release strategy at itme level.

    You have to include a charecteristic for cost center and create release strategies respectively.

    hence you can assign a manager who is responseible for a set of cost centers.

    u have lols of documents available if you are new for release strategy.

    BR

    SD.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.