on 02-24-2009 1:27 AM
Hi all
I was looking at the OSS note 156933 to solve my scheduling dates relevent to operations. In note it mentioned that, i have to introduce new basic unit of measure, such as Day and
1 workday = 8 hours. This can solve my problem .
SO i need help configuring the new Unit of measure and where can i assign 1 work day = 8 hours in the CUNI tocode.
Please advice.
Quantum.
Hi,
In the CUNI transaction just create new unit of measure (WD - Work Day in your case) and assign the alternative unit of measure settings (say 1 WD = 8 HR) at the material master level.
Hope this helps.
Thanks
nagarajan