Unit of measure

Hi all

I was looking at the OSS note 156933 to solve my scheduling dates relevent to operations. In note it mentioned that, i have to introduce new basic unit of measure, such as Day and

1 workday = 8 hours. This can solve my problem .

SO i need help configuring the new Unit of measure and where can i assign 1 work day = 8 hours in the CUNI tocode.

Please advice.

Quantum.

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Posted on Feb 25, 2009 at 04:55 PM

    Hi,

    In the CUNI transaction just create new unit of measure (WD - Work Day in your case) and assign the alternative unit of measure settings (say 1 WD = 8 HR) at the material master level.

    Hope this helps.

    Thanks

    nagarajan

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi Nagarajan

      Thanks for your input, I have done the change already by changing the conversion factor in CUNI. But i have done in different way, i am not using this unit of measure in Material but in work center.

      Thanks,

      Quantum.

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.