Hi everyone

I have a problem whit the multiple account assigment when i try to make a PO for Asset, whit planned delivery cost because the systems shows messange that cannot use a planned delivery cost with multiple account assigment.

I don´t not why is the message, if i want to make a PO for 40 asset with one planned delivery cost in PO header.

With this message i have to make one item line for one asset and then put the planned delivery cost in PO header.

thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi JOse,

Please go to t.code SPRO:

Materials Management->Purchasing->Account Assignment->Maintain Account Assignment Categories

Check the box - Del. cost separate as required.

regards,

SD

Answers (5)

Answers (5)

0 Kudos

hanks for your answer, >I think that SAP must be considered change this procees and allow multiple account assigment in Asset.

Former Member
0 Kudos

Hi,

This is a standard SAP functionality.We cannot use a planned delivery cost with multiple account assigment.

Regards,

Manish

0 Kudos

Hi Manish

The warnning massage is: "No delivery costs can be posted in case of multiple account assignment"

Message no. 06356

best regards

Former Member
0 Kudos

Hi,

Its a standard functionality.Let me know the message number with description.

Regards,

Manish

0 Kudos

Thanks but, already i was use this field in check the box - Del. cost separate as required. And the warnning message is the same