I have made a MTS scenario for the configurable materials with characteristics planning.
I have entered forecasting in MD61 for the materials which are configured for color. The materials are also batch managed and valuated. I could not find the reduction in PIRs when the PGI was made for these FG stocks.
I have tried with strategy 10 and 40 also. The material master data is correct. The requirement class I checked was 30 and 50 for these strategies. I made changes in those classes to add configuration.
In requirement classes setting for configuration, I added * (Configuration allowed), and Ind Req Reduction ticked.
Please tell me what other things I need to check to do this.
Thanks in advance.
Regards,
Sumeet