Dear All,

I have made a MTS scenario for the configurable materials with characteristics planning.

I have entered forecasting in MD61 for the materials which are configured for color. The materials are also batch managed and valuated. I could not find the reduction in PIRs when the PGI was made for these FG stocks.

I have tried with strategy 10 and 40 also. The material master data is correct. The requirement class I checked was 30 and 50 for these strategies. I made changes in those classes to add configuration.

In requirement classes setting for configuration, I added * (Configuration allowed), and Ind Req Reduction ticked.

Please tell me what other things I need to check to do this.

Thanks in advance.

Regards,

Sumeet