Hi,experts
Good Sunday.
I finished the configuration of PR release procedure,but it is not effective as I created PR.
My scenario of PR release procedure:
1) Create two characteristics Z_WERKS,Z_GSWRT mapped by CEBAN-WERKS and CEBAN-GSWRT.
2) Create a class Z_PR_REL_CLASS includes above two characteristics.
3) Create a release group named AA refer to class Z_PR_REL_CLASS.
4) Create three release codes L1,L2 and L3.
5) Create two release strategy S1,S2
S1 limits the PR total item value small and equal than 1000 RMB.
S2 limits the PR total item value great than 1000 RMB.
Yes, I finished the details of the above configurations,
However, I created several PRs with the various total item values,the corresponding S2 release procedure is not adopted.
I don't know what the problem is.