Hi all,
I have a scenario where company is procuring an asset and the vendor from which the company is procuring the Asset is sending that Asset in different parts like for a whole machinery the vendor is dismantling at its end and then assemble inside the client premisis but sending in different shipements
Now requirement is In the PO there is only one line item with Asset code, GR is to be done for all the Dismantled parts and for that parts material master is not maintained, on some of the dismantled parts excise entry is required.
When is Asset is assembled i have to show the GR entry for complete asset and have to update my RG23C register for both Part1 and Part2 entry.
How to map such a scenario??
Regards
Akshit