Dispatch Scheduling Error

Hi All,

When I am dispatching an activity through CM22, I am getting error "Error during scheduling of splits-An error ocurred during scheduling of splits.The cause of the error may be a person is not available during the split period"

Does this is due to the person to which the activity is assigned doesnt have available time for that particular date and time of disptach in the Work Centre.

Your help will be appreciated.

Thanks,

Mohammed

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • avatar image
    Former Member
    Feb 21, 2009 at 03:26 PM

    hi Mohammed ,

    you can first de-allocate your activity and try to change the work center capacity or the reduce the activity capacity requirements and then dispatch the acitivity... once u dispatch activity status wuld be DSPT ..