Former Member
Feb 21, 2009 at 06:08 AM

Job for Preventive Maintenance Order

37 Views

Dear Experts

I had scheduled the job of preventive maintenance orders .This job is taking so much time to execute enen only 2000 plan numbers are stored in this.

As i analised the problem i found that there are few plans in which schdule start date is in past say in 2006 and cycle is for 7 years .But as plan call date lies in future i.e in 2013 so there is message is shown as "Date 31.12.2013 is before the end of the factory calendar IN".Please guide me how to resolve this issue permanently.

Thanx in Advance

Raj Jindal.