HI PP Guys,
My client is doing MRP Run on WBS elements. Their scenario is like they attached the materials to the WBS elements & run the MRP. But they are attaching materials as an when the BOM is get reay. Now the problem is if they are attaching material "A" toady, & run the MRP, system explode the BOM & giving the PR for all raw materials in the BOM. Purchase dept converted the PR into PO.
Now next day Plannig dept attaching another material,say "B" to the same WBS element, & run the MRP. This time system generated the PR for the raw materials in the BOM of "B" as well as the raw materials in the BOM of "A". But if the PO for all the materials in the BOM of "A" is exsting then how the systme i generating the PR for the same requirement.
Pl help me....
Thanks,
Regards,
Sachin Patil